Construction Activity for January 3 - January 14, 2022

activity location description start date end date noise level dust level traffic impact
Traffic Control Plan Implementation Veteran Ave Nightly (8:00 p.m. to 6:00 a.m.) lane closures to accommodate work between Weyburn Ave and Wilshire Blvd 11/15/21 4/1/22 Low Low Moderate
Site Construction Wilshire fire station Install new sewer line and backfill 12/27/21 1/3/22 Moderate Low High
Site Construction Wilshire-Kinross Base paving 12/30/21 1/6/22 Moderate  Moderate High
Demolition Fire station Demolish and reconstruct manholes 1/10/22 1/14/22 Moderate  Low High