Construction Activity for April 25 - May 23, 2022

Activity Location Description Start
Date
End
Date
Noise
Level
Dust
Level
Traffic
Impact
Site Construction Site (inside fence) Private Dr (Gate 2) road pavement
(road closure
5/23/22 7/1/22 Moderate Moderate High
Site Construction Site (inside fence) Building 2 site work (road closure) ongoing 4/29/22 Moderate Moderate High