Construction Activity for July 12- July 20, 2021

Activity Location Description Start
Date
End
Date
Noise
Level
Dust
Level
Traffic
Impact
Material deliveries De Neve Drive / Southern Regional Library Drive Material deliveries (framing, drywall, casework etc) December 2018 7/15/21 low low moderate
Grading North & South Tower  Exterior grading & Hardscape 11/30/20 7/22/21 low low low
Bridge Lights Bridge Rough-in conduits and install fixtures 6/28/21 7/13/21 moderate moderate low
Landscaping Entire Site Grading, Irrigation, Trees 3/22/21 7/30/21 moderate moderate moderate
Demo & re-pour SRL Demolition of sidewalk, asphalt, and re-pour 6/22/21 7/22/21 moderate moderate high
Pave SRL  SRL Asphalt SRL and De Neve 7/16/21 7/20/21 high high high