Construction Activity for July 12- July 20, 2021
Activity | Location | Description | Start Date |
End Date |
Noise Level |
Dust Level |
Traffic Impact |
---|---|---|---|---|---|---|---|
Material deliveries | De Neve Drive / Southern Regional Library Drive | Material deliveries (framing, drywall, casework etc) | December 2018 | 7/15/21 | low | low | moderate |
Grading | North & South Tower | Exterior grading & Hardscape | 11/30/20 | 7/22/21 | low | low | low |
Bridge Lights | Bridge | Rough-in conduits and install fixtures | 6/28/21 | 7/13/21 | moderate | moderate | low |
Landscaping | Entire Site | Grading, Irrigation, Trees | 3/22/21 | 7/30/21 | moderate | moderate | moderate |
Demo & re-pour | SRL | Demolition of sidewalk, asphalt, and re-pour | 6/22/21 | 7/22/21 | moderate | moderate | high |
Pave SRL | SRL | Asphalt SRL and De Neve | 7/16/21 | 7/20/21 | high | high | high |