Construction Activity for October 4 - 10, 2020
Activity | Location | Description | Start Date | End Date | Noise Level | Dust Level | Traffic Impact |
---|---|---|---|---|---|---|---|
Concrete work | Exterior | The contractor will remove the retaining wall formwork | 10/05/20 | 10/05/20 | low | low | none |
Concrete work | Exterior | The contractor will install rebar for the stairs and walkway | 10/05/20 | 10/08/20 | low | low | none |
Concrete work | Exterior | The contractor will install formwork for the stairs and walkway | 10/06/20 | 10/08/20 | low | low | none |
Concrete work | Exterior | The contractor will begin concrete pouring for the stairs and walkway | 10/08/20 | 10/09/20 | moderate | low | none |
Electrical work | Exterior | The contractor will install the light post | 10/09/20 | 10/09/20 | low | low | none |